| Daytime Noise Monitoring Results | |||||||||||||
| Station M7a, Wah Ming House | |||||||||||||
| Date | Start Time | End Time | Weather | Noise level (dB(A)), 30 min | Major Construction Noise Source(s) Observed | Other Noise Source(s) Observed | Remarks | Temp. (°C) | Wind Speed (m/s) | Noise Meter Model / ID | Calibrator Model / ID | ||
| Leq | L10 | L90 | |||||||||||
| 02-Dec-13 | 09:34 | 10:04 | Fine | 66 | 67 | 64 | N.A | renovation of stairs and platform in the Wah Chun House | N.A | 17.7 | <5 | B&K 2238 S/N : 2684503 | B&K 4231 S/N: 3004068 |
| 12-Dec-13 | 09:22 | 09:52 | Fine | 71 | 74 | 60 | N.A | renovation of stairs and platform in the Wah Chun House | N.A | 18 | <5 | B&K 2238 S/N : 2684503 | B&K 4231 S/N: 3004068 |
| 18-Dec-13 | 09:30 | 10:00 | Fine | 73 | 78 | 62 | N.A | Sheet piling operation in adjacent site and renovation of stairs and platform in the Wah Chun House | N.A | 10.9 | <5 | B&K 2238 S/N : 2684503 | B&K 4231 S/N: 3004068 |
| 23-Dec-13 | 09:43 | 10:13 | Fine | 66 | 68 | 63 | N.A | renovation of stairs and platform in the Wah Chun House | N.A | 14.6 | <5 | B&K 2238 S/N : 2684503 | B&K 4231 S/N: 3004068 |
| 30-Dec-13 | 09:24 | 09:54 | Fine | 65 | 68 | 61 | N.A | renovation of stairs and platform in the Wah Chun House | N.A | 13.8 | <5 | B&K 2238 S/N : 2684503 | B&K 4231 S/N: 3004068 |